Lights Ferry Roundabout
Georgia Development Partners was contracted by the City of Flowery Branch, GA to perform complete reconstruction of their central downtown business district road and right of way including: Demolition, Traffic Control, Road Realignment, Lighting, Paving, Clearing, Concrete Flatwork, Architectural Concrete, Sewer, Storm, & Water Relocation, Poured & Placed Walls
Client: City of Flowery Branch
Location: City of Flowery Branch, GA
Cost: $1,200,000
Roles: General Contractor, Utility Contractor