Hickory Road and Holly Springs Parkway Pedestrian Improvements
Georgia Development Partners was contracted by the City of Holly Springs to complete pedestrian improvements throughout the downtown area. The project consisted of shoulder improvements to construct a 5' sidewalk along Holly Springs Parkway and Hickory Road, installed concrete box culvert with wingwalls and additional components of storm drainage.
Client: City of Holly Springs
Location: City of Holly Springs, GA
Cost: $2,200,000
Period: 2016-2017
Roles: General Contractor, Utility Contractor
Printable Version: View PDF
Location: City of Holly Springs, GA
Cost: $2,200,000
Period: 2016-2017
Roles: General Contractor, Utility Contractor
Printable Version: View PDF